The good news is that Casino water features are full and operating and we even have waterfalls where they weren't planned. Travel on-site is a bit hazzardous...
With warm-dry weather predicted, the project will regain the couple days lost. Focus is finish of exterior studs, sheathing and getting the shell closed in the next couple weeks. Concrete parking and roadway are being finished on the NW,N and NE sides of the building. Iron is all in with the exception of the Porte Cochere and exterior finishes are already being applied on the backside of the Casino. You will continue to see fine-grading, parking lot and landscape underway.
Other stuff - Website is being designed and should be up in May. It will direct potential suppliers and employees in how to apply and keep you up to date on overall progress. Expect most employment to be in late fall 2009.